6 inches of water to clear out of our basement,luckily no major damadges as plasterboarding was just about to start
Disaster strikes on 2nd Febuary. Before the building is water tight the site and BASEMENT floods
Steel mesh laid ready for the screed on special plastic chairs,thre steel helps heating distribution
Pipework set to return to manifolds to give zoning and control to each area
Our bedroom finally constructed as a shell with great views
Pipes installed with a tighter ratio and concentration for more efficient heating from the solar panels
Under floor heating is installed on a special thermo insulation
Polishing starts on the basement floor
Special screed poured so it can be polished
Basement floor prepared for screed
Roof application starts with the special fibre-glass mesh
Our office has double window aspect
Land cleared and levelled on back elevation
Inside of the hood constructed from steel and plaster
Bookcase finished
Terrace column details
A layer of water proof plaster then applied to all the roofs in preperation for the plastic roof paint
Basement tanking completed
Large bookcase is constructed in main lounge
Finished 4m high ceiling in the Lounge
Old Sabina heads used as lintel details over doorways
The fireplace hood starts to be constructed
Detail cross joint of sabina and capital
Thursday, 2 February 2012
January 2012 and the front terrace starts to take shape
Rounds are added to the roof pelmets to soften facade
Internal tanking sprayed by hydraulic machine
Basement being prepared for internal tanking
The top bedroom roof is ready for the concrete pour
Each claraboya has insulated returns to prvent condensation and heat loss
Conrete levels formed to give falls to the roofs
Interenal walls constructed in blockwork
Insulation and metal caging starts on the roofs
The view from the front ,looking at our bedroom
The view from our bedroom window
Stair void installed with 2 light wells above
Ceiling claraboyas to create lots of natural light
The beam had to be cut in situ to fit perfectly
An 8 metre main lounge sabina was craned into position
Kitchen sabinas finished
Nat's pilates studio starts to take shape
Shell completed December week 2 ready to start internal fit out
Our new home starts to take shape
Gary finishes preparing the sabinas
Tricky work pouring concrete into each pocket
Sabinas notched into blocwork walls
The main sabinas are lifted into place
A special cleever is used to sive the terrain into top quality topsoil
Top floor starts to be constructed
Land being cleared for pool area and landscaping
Window shape mocked up with rustic render appearance