Its traditional to mark the floor infront of the entrance to a new house. The most productive week since starting on site.
The blockwork walls will start to go up next week
Concrete slab gets laid only 5 weeks after starting on site, with 3 days of that programme lost due to bad weather
The boys take a well deserved lunch break before the slabs go down and a litre of Spanish beer
Every floor level,which is at a different levels has to be laid at different stages so that the slabs overlap
Elecrical ducts and in ground services laid before the floor slab is cast
Props and supports installed to start the basement roof and ground floor of the bedrooms
Blocwork is laid onto the new footings,providing the divisions between the different floor levels
A different type of concrete was poured and laid on the basement floor which has an additive to help dampcourse and water ingress
2 layers of plastic sheeting laid ontop of crushed sand and coral which is packed down first and then metal mesh installed, lifted off the plastic sheet on small packers
Footings completed by 4.00 pm
1 man poured all the foundations on his own !!!!
All the cages made up previously were dropped into the footings,packed up off the capping concrete base and tied with connecting bars
A massive pump was hired to lay the concrete footings.In total 12 large concrete lorrys delivered all of the fast setting concrete and this was laid by 1 man in just under 4 hours
Sunday, 13 November 2011
Special plastic protection added to the outer walls as back filling is taking place
All the footings and cages are now installed and concrete is due to be poured for the main finca construction to tie into the basement
A water bar detail is installed before the second skin shutter is installed and the concrete poured. This will provide a barrier which swells if water comes into contact with the product, if there is ever any flooding that occurs at low level
An outer steel box is created giving a real feel of the size the basement area
Outer skin installed first,locked onto dowel pins drilled into footings
Shuttering craned into position to start the basement wall erection
Position bars for the metal shuttering carefully marked out and placed into concrete footings
Both layers of caging now completed and ready for the concrete shuttering
First outer layer of caging installed
Footing cages finished,now ready for vertical cages
Vertical tie bars are installed ready to take the caging which creates the basement vertical walls
A good first week. After week 1, we are on programme and the Spanish builders have performed very well.The owner of the concrete company is on site twice a day and is taking a real interest and pride in what he is doing.
Cage footings are then all craned into position in the basement
A MOMENTOUS MILESTONE !!!!!!
After 6 years of planning battles,purchasing the land and finding a contractor we at last lay our first piece of concrete
The gruer arrives to pour the concrete cap in the footings
Structural cages all lined up awaiting the crane to lift them into place
Basement footings marked out ready to be dug
All of the cages are made up ready to drop into the basement footings
Site boards designed by my talented sister
Trying different site set ups, rock wall camoflage could be a good option for rental period so it doesn't look to much like a building site
Digger creates a ramp to allow access into the basement area
Thursday, 10 November 2011
The basement dig had to go though 3 different stratas of rock and took four times longer than we anticipated